Nameplate capacity
130 MW
Rank in Wyoming
#25
of 71 plants
In service since
2010
October 2010
Details
- Primary fuel
- Wind
- Technology
- Onshore Wind Turbine
- Operator
- PacifiCorp
- County
- Carbon County
- Generating units
- 1
- Share of state capacity
- 1.02%
- Rank among wind plants in Wyoming
- #15 of 28
- EIA plant code
- 57299
Generating units
| Unit | Technology | Nameplate | Summer | Online | Status |
|---|---|---|---|---|---|
| 1 | Onshore Wind Turbine | 130 MW | 111 MW | 2010 | Operating |
Nameplate is the maximum rated output; summer capacity is what the unit can reliably deliver on a hot day, which is typically lower.
Similarly sized plants in Wyoming
| Cedar Springs III | Wind | 133 MW |
| Neil Simpson II | Coal | 130 MW |
| Anticline Wind | Wind | 124 MW |
| High Plains | Wind | 122 MW |
About this data
From EIA’s inventory of operable generators, May 2026 release. Capacity is nameplate — the maximum rated output of the equipment, not what the plant actually generates over a year, which depends on how often it runs. A 130 MW solar plant and a 130 MW nuclear plant have the same entry here and produce very different amounts of electricity.
“In service since” is the earliest in-service date among the units still listed, so a site rebuilt around newer equipment can read as younger than the site itself. All Wyoming power plants · What Wyoming actually generates