Seminole Energy
Other power plant · Seminole County, Florida
Nameplate capacity
4.8 MW
Rank in Florida
#311
of 346 plants
In service since
2007
November 2007
Details
- Primary fuel
- Other
- Technology
- Landfill Gas
- Operator
- NextEra Renewable Fuels, LLC
- County
- Seminole County
- Generating units
- 3
- Share of state capacity
- 0.01%
- Rank among other plants in Florida
- #35 of 41
- EIA plant code
- 61780
Generating units
| Unit | Technology | Nameplate | Summer | Online | Status |
|---|---|---|---|---|---|
| ENG1 | Landfill Gas | 1.6 MW | 1.6 MW | 2007 | Operating |
| ENG2 | Landfill Gas | 1.6 MW | 1.6 MW | 2007 | Operating |
| ENG3 | Landfill Gas | 1.6 MW | 1.6 MW | 2007 | Operating |
Nameplate is the maximum rated output; summer capacity is what the unit can reliably deliver on a hot day, which is typically lower.
Similarly sized plants in Florida
| ACE-Stanton PV | Solar | 4.8 MW |
| Central District Wastewater Treat Plant | Other | 4.8 MW |
| Springhill Gas Recovery Plant | Other | 4.8 MW |
| ACE-Stanton A PV | Solar | 4.1 MW |
About this data
From EIA’s inventory of operable generators, May 2026 release. Capacity is nameplate — the maximum rated output of the equipment, not what the plant actually generates over a year, which depends on how often it runs. A 4.8 MW solar plant and a 4.8 MW nuclear plant have the same entry here and produce very different amounts of electricity.
“In service since” is the earliest in-service date among the units still listed, so a site rebuilt around newer equipment can read as younger than the site itself. All Florida power plants · What Florida actually generates