Home / Power plants / California / Eland Solar & Storage Center, Phase 2 Hy

Eland Solar & Storage Center, Phase 2 Hy

Solar power plant · Kern County, California

Nameplate capacity
458 MW
Rank in California
#45
of 1,897 plants
In service since
2025
July 2025

Details

Primary fuel
Solar
Technology
Solar Photovoltaic
Operator
69SV 8me LLC
County
Kern County
Generating units
2
Share of state capacity
0.42%
Rank among solar plants in California
#6 of 937
EIA plant code
61169

Generating units

Individual generating units at Eland Solar & Storage Center, Phase 2 Hy
UnitTechnologyNameplateSummerOnlineStatus
69SV8Solar Photovoltaic308 MW200 MW2025Operating
61169Batteries150 MW150 MW2025Operating

Nameplate is the maximum rated output; summer capacity is what the unit can reliably deliver on a hot day, which is typically lower.

Similarly sized plants in California

About this data

From EIA’s inventory of operable generators, May 2026 release. Capacity is nameplate — the maximum rated output of the equipment, not what the plant actually generates over a year, which depends on how often it runs. A 458 MW solar plant and a 458 MW nuclear plant have the same entry here and produce very different amounts of electricity.

“In service since” is the earliest in-service date among the units still listed, so a site rebuilt around newer equipment can read as younger than the site itself. All California power plants · What California actually generates