Sherwood H Smith Jr Energy Complex
Natural gas power plant · Richmond County, North Carolina
Details
- Primary fuel
- Natural gas
- Technology
- Natural Gas Fired Combined Cycle
- Operator
- Duke Energy Progress - (NC)
- County
- Richmond County
- Generating units
- 11
- Share of state capacity
- 5.60%
- Rank among natural gas plants in North Carolina
- #3 of 22
- EIA plant code
- 7805
Generating units
| Unit | Technology | Nameplate | Summer | Online | Status |
|---|---|---|---|---|---|
| ST5 | Natural Gas Fired Combined Cycle | 271 MW | 252 MW | 2011 | Operating |
| 001 | Natural Gas Fired Combustion Turbine | 199 MW | 165 MW | 2001 | Operating |
| 002 | Natural Gas Fired Combustion Turbine | 199 MW | 164 MW | 2001 | Operating |
| 003 | Natural Gas Fired Combustion Turbine | 199 MW | 160 MW | 2001 | Operating |
| 004 | Natural Gas Fired Combustion Turbine | 199 MW | 159 MW | 2001 | Operating |
| 6 | Natural Gas Fired Combustion Turbine | 199 MW | 152 MW | 2002 | Operating |
| 7 | Natural Gas Fired Combined Cycle | 199 MW | 152 MW | 2002 | Operating |
| 8 | Natural Gas Fired Combined Cycle | 199 MW | 152 MW | 2002 | Operating |
| ST4 | Natural Gas Fired Combined Cycle | 196 MW | 171 MW | 2002 | Operating |
| 10 | Natural Gas Fired Combined Cycle | 191 MW | 178 MW | 2011 | Operating |
| 9 | Natural Gas Fired Combined Cycle | 191 MW | 178 MW | 2011 | Operating |
Nameplate is the maximum rated output; summer capacity is what the unit can reliably deliver on a hot day, which is typically lower.
Similarly sized plants in North Carolina
| McGuire | Nuclear | 2,441 MW |
| Lincoln Combustion | Natural gas | 2,290 MW |
| Marshall (NC) | Natural gas | 2,119 MW |
| Brunswick Nuclear | Nuclear | 2,003 MW |
About this data
From EIA’s inventory of operable generators, May 2026 release. Capacity is nameplate — the maximum rated output of the equipment, not what the plant actually generates over a year, which depends on how often it runs. A 2,245 MW solar plant and a 2,245 MW nuclear plant have the same entry here and produce very different amounts of electricity.
“In service since” is the earliest in-service date among the units still listed, so a site rebuilt around newer equipment can read as younger than the site itself. All North Carolina power plants · What North Carolina actually generates