Home / Power plants / Florida / CSL Gas Recovery

CSL Gas Recovery

Other power plant · Broward County, Florida

Nameplate capacity
11 MW
Rank in Florida
#282
of 346 plants
In service since
1989
March 1989

Details

Primary fuel
Other
Technology
Landfill Gas
Operator
WM Renewable Energy LLC
County
Broward County
Generating units
4
Share of state capacity
0.01%
Rank among other plants in Florida
#29 of 41
EIA plant code
50572

Generating units

Individual generating units at CSL Gas Recovery
UnitTechnologyNameplateSummerOnlineStatus
GEN1Landfill Gas3.0 MW2.9 MW1989Operating
GEN2Landfill Gas3.0 MW2.9 MW1989Operating
GEN3Landfill Gas3.0 MW2.9 MW1989Operating
GEN4Landfill Gas2.2 MW2.2 MW2000Operating

Nameplate is the maximum rated output; summer capacity is what the unit can reliably deliver on a hot day, which is typically lower.

Similarly sized plants in Florida

Jax LNGNatural gas13 MW
South Energy CenterNatural gas12 MW
TrentonBattery storage11 MW
Florida's Natural GrowersNatural gas11 MW

About this data

From EIA’s inventory of operable generators, May 2026 release. Capacity is nameplate — the maximum rated output of the equipment, not what the plant actually generates over a year, which depends on how often it runs. A 11 MW solar plant and a 11 MW nuclear plant have the same entry here and produce very different amounts of electricity.

“In service since” is the earliest in-service date among the units still listed, so a site rebuilt around newer equipment can read as younger than the site itself. All Florida power plants · What Florida actually generates