GMP Solar/Storage-Ferrisburgh Hybrid
Solar power plant · Addison County, Vermont
Nameplate capacity
7.0 MW
Rank in Vermont
#25
of 117 plants
In service since
2019
September 2019
Details
- Primary fuel
- Solar
- Technology
- Solar Photovoltaic
- Operator
- Green Mountain Power Corp
- County
- Addison County
- Generating units
- 2
- Share of state capacity
- 0.78%
- Rank among solar plants in Vermont
- #2 of 53
- EIA plant code
- 62382
Generating units
| Unit | Technology | Nameplate | Summer | Online | Status |
|---|---|---|---|---|---|
| GMPSF | Solar Photovoltaic | 5.0 MW | 5.0 MW | 2019 | Operating |
| GMPBF | Batteries | 2.0 MW | 2.0 MW | 2019 | Operating |
Nameplate is the maximum rated output; summer capacity is what the unit can reliably deliver on a hot day, which is typically lower.
Similarly sized plants in Vermont
| Chace Mill Winooski One | Hydro | 7.5 MW |
| Milton | Hydro | 7.4 MW |
| GMP Solar/Storage-Milton Hybrid | Solar | 7.0 MW |
| Proctor | Hydro | 6.9 MW |
About this data
From EIA’s inventory of operable generators, May 2026 release. Capacity is nameplate — the maximum rated output of the equipment, not what the plant actually generates over a year, which depends on how often it runs. A 7.0 MW solar plant and a 7.0 MW nuclear plant have the same entry here and produce very different amounts of electricity.