Nameplate capacity
4.2 MW
Rank in Utah
#86
of 131 plants
In service since
1958
August 1958
Details
- Primary fuel
- Hydro
- Technology
- Conventional Hydroelectric
- Operator
- Garkane Energy Coop, Inc
- County
- Garfield County
- Generating units
- 3
- Share of state capacity
- 0.04%
- Rank among hydro plants in Utah
- #9 of 29
- EIA plant code
- 3699
Generating units
| Unit | Technology | Nameplate | Summer | Online | Status |
|---|---|---|---|---|---|
| 1 | Conventional Hydroelectric | 1.4 MW | 1.4 MW | 1958 | Operating |
| 2 | Conventional Hydroelectric | 1.4 MW | 1.4 MW | 1958 | Operating |
| 3 | Conventional Hydroelectric | 1.4 MW | 1.4 MW | 1961 | Operating |
Nameplate is the maximum rated output; summer capacity is what the unit can reliably deliver on a hot day, which is typically lower.
Similarly sized plants in Utah
| Trans-Jordan Generating Station | Other | 4.8 MW |
| Echo Dam | Hydro | 4.4 MW |
| Gateway | Hydro | 4.0 MW |
| Spanish Fork Community Solar | Solar | 4.0 MW |
About this data
From EIA’s inventory of operable generators, May 2026 release. Capacity is nameplate — the maximum rated output of the equipment, not what the plant actually generates over a year, which depends on how often it runs. A 4.2 MW solar plant and a 4.2 MW nuclear plant have the same entry here and produce very different amounts of electricity.
“In service since” is the earliest in-service date among the units still listed, so a site rebuilt around newer equipment can read as younger than the site itself. All Utah power plants · What Utah actually generates