WED Coventry 1
Wind power plant · Kent County, Rhode Island
Nameplate capacity
1.5 MW
Rank in Rhode Island
#96
of 110 plants
In service since
2016
October 2016
Details
- Primary fuel
- Wind
- Technology
- Onshore Wind Turbine
- Operator
- WED Coventry One, LLC
- County
- Kent County
- Generating units
- 1
- Share of state capacity
- 0.06%
- Rank among wind plants in Rhode Island
- #14 of 19
- EIA plant code
- 59301
Generating units
| Unit | Technology | Nameplate | Summer | Online | Status |
|---|---|---|---|---|---|
| WEDC1 | Onshore Wind Turbine | 1.5 MW | 1.5 MW | 2016 | Operating |
Nameplate is the maximum rated output; summer capacity is what the unit can reliably deliver on a hot day, which is typically lower.
Similarly sized plants in Rhode Island
| Pawtucket Hydroelectric Project | Hydro | 1.6 MW |
| Green Providence Wind I, LLC | Wind | 1.5 MW |
| WED Coventry 3 | Wind | 1.5 MW |
| WED Coventry 4 | Wind | 1.5 MW |
About this data
From EIA’s inventory of operable generators, May 2026 release. Capacity is nameplate — the maximum rated output of the equipment, not what the plant actually generates over a year, which depends on how often it runs. A 1.5 MW solar plant and a 1.5 MW nuclear plant have the same entry here and produce very different amounts of electricity.