Traverse Wind Project, LLC
Wind power plant · Custer County, Oklahoma
Nameplate capacity
999 MW
Rank in Oklahoma
#11
of 147 plants
In service since
2022
April 2022
Details
- Primary fuel
- Wind
- Technology
- Onshore Wind Turbine
- Operator
- Southwestern Electric Power Co
- County
- Custer County
- Generating units
- 1
- Share of state capacity
- 2.74%
- Rank among wind plants in Oklahoma
- #1 of 70
- EIA plant code
- 63479
Generating units
| Unit | Technology | Nameplate | Summer | Online | Status |
|---|---|---|---|---|---|
| GEN1 | Onshore Wind Turbine | 999 MW | 999 MW | 2022 | Operating |
Nameplate is the maximum rated output; summer capacity is what the unit can reliably deliver on a hot day, which is typically lower.
Similarly sized plants in Oklahoma
| Riverside (OK) | Natural gas | 1,122 MW |
| Chouteau | Natural gas | 1,070 MW |
| Green Country Power Station | Natural gas | 904 MW |
| Skeleton Creek Energy Center Hybrid | Battery storage | 752 MW |
About this data
From EIA’s inventory of operable generators, May 2026 release. Capacity is nameplate — the maximum rated output of the equipment, not what the plant actually generates over a year, which depends on how often it runs. A 999 MW solar plant and a 999 MW nuclear plant have the same entry here and produce very different amounts of electricity.
“In service since” is the earliest in-service date among the units still listed, so a site rebuilt around newer equipment can read as younger than the site itself. All Oklahoma power plants · What Oklahoma actually generates