Home / Power plants / Oklahoma / Sundance Wind Project, LLC

Sundance Wind Project, LLC

Wind power plant · Woods County, Oklahoma

Nameplate capacity
199 MW
Rank in Oklahoma
#53
of 147 plants
In service since
2021
April 2021

Details

Primary fuel
Wind
Technology
Onshore Wind Turbine
Operator
Public Service Co of Oklahoma
County
Woods County
Generating units
1
Share of state capacity
0.55%
Rank among wind plants in Oklahoma
#29 of 70
EIA plant code
63489

Generating units

Individual generating units at Sundance Wind Project, LLC
UnitTechnologyNameplateSummerOnlineStatus
GEN1Onshore Wind Turbine199 MW199 MW2021Operating

Nameplate is the maximum rated output; summer capacity is what the unit can reliably deliver on a hot day, which is typically lower.

Similarly sized plants in Oklahoma

About this data

From EIA’s inventory of operable generators, May 2026 release. Capacity is nameplate — the maximum rated output of the equipment, not what the plant actually generates over a year, which depends on how often it runs. A 199 MW solar plant and a 199 MW nuclear plant have the same entry here and produce very different amounts of electricity.

“In service since” is the earliest in-service date among the units still listed, so a site rebuilt around newer equipment can read as younger than the site itself. All Oklahoma power plants · What Oklahoma actually generates