Home / Power plants / Ohio / RP Wind

RP Wind

Wind power plant · Logan County, Ohio

Nameplate capacity
3.4 MW
Rank in Ohio
#160
of 219 plants
In service since
2013
December 2013

Details

Primary fuel
Wind
Technology
Onshore Wind Turbine
Operator
RWE Clean Energy
County
Logan County
Generating units
1
Share of state capacity
0.01%
Rank among wind plants in Ohio
#16 of 22
EIA plant code
58630

Generating units

Individual generating units at RP Wind
UnitTechnologyNameplateSummerOnlineStatus
RPOHOnshore Wind Turbine3.4 MW3.4 MW2013Operating

Nameplate is the maximum rated output; summer capacity is what the unit can reliably deliver on a hot day, which is typically lower.

Similarly sized plants in Ohio

About this data

From EIA’s inventory of operable generators, May 2026 release. Capacity is nameplate — the maximum rated output of the equipment, not what the plant actually generates over a year, which depends on how often it runs. A 3.4 MW solar plant and a 3.4 MW nuclear plant have the same entry here and produce very different amounts of electricity.

“In service since” is the earliest in-service date among the units still listed, so a site rebuilt around newer equipment can read as younger than the site itself. All Ohio power plants · What Ohio actually generates