Nameplate capacity
45 MW
Rank in Ohio
#83
of 219 plants
In service since
2025
January 2025
Details
- Primary fuel
- Solar
- Technology
- Solar Photovoltaic
- Operator
- Geronimo Power
- County
- Ross County
- Generating units
- 1
- Share of state capacity
- 0.13%
- Rank among solar plants in Ohio
- #31 of 76
- EIA plant code
- 67166
Generating units
| Unit | Technology | Nameplate | Summer | Online | Status |
|---|---|---|---|---|---|
| FYTSL | Solar Photovoltaic | 45 MW | 45 MW | 2025 | Operating |
Nameplate is the maximum rated output; summer capacity is what the unit can reliably deliver on a hot day, which is typically lower.
Similarly sized plants in Ohio
| Racine | Hydro | 47 MW |
| Central Utility Plant Cincinnati | Natural gas | 47 MW |
| Bryan (OH) | Natural gas | 39 MW |
| Piqua Power Plant | Other | 36 MW |
About this data
From EIA’s inventory of operable generators, May 2026 release. Capacity is nameplate — the maximum rated output of the equipment, not what the plant actually generates over a year, which depends on how often it runs. A 45 MW solar plant and a 45 MW nuclear plant have the same entry here and produce very different amounts of electricity.
“In service since” is the earliest in-service date among the units still listed, so a site rebuilt around newer equipment can read as younger than the site itself. All Ohio power plants · What Ohio actually generates