Pilot Mountain Solar, LLC
Solar power plant · Stokes County, North Carolina
Details
- Primary fuel
- Solar
- Technology
- Solar Photovoltaic
- Operator
- USF Essex Lessor, LLC
- County
- Stokes County
- Generating units
- 1
- Share of state capacity
- 0.01%
- Rank among solar plants in North Carolina
- #521 of 758
- EIA plant code
- 63835
Generating units
| Unit | Technology | Nameplate | Summer | Online | Status |
|---|---|---|---|---|---|
| PV1 | Solar Photovoltaic | 4.9 MW | 4.9 MW | 2020 | Operating |
Nameplate is the maximum rated output; summer capacity is what the unit can reliably deliver on a hot day, which is typically lower.
Similarly sized plants in North Carolina
| Nickelson Solar 2 | Solar | 4.9 MW |
| North Carolina Solar III LLC | Solar | 4.9 MW |
| Rockfish Solar | Solar | 4.9 MW |
| Royal Solar | Solar | 4.9 MW |
About this data
From EIA’s inventory of operable generators, May 2026 release. Capacity is nameplate — the maximum rated output of the equipment, not what the plant actually generates over a year, which depends on how often it runs. A 4.9 MW solar plant and a 4.9 MW nuclear plant have the same entry here and produce very different amounts of electricity.