Home / Power plants / California / Nicolis Solar PV Plant

Nicolis Solar PV Plant

Solar power plant · Tulare County, California

Nameplate capacity
20 MW
Rank in California
#674
of 1,897 plants
In service since
2016
September 2016

Details

Primary fuel
Solar
Technology
Solar Photovoltaic
Operator
Arevon Energy, Inc.
County
Tulare County
Generating units
1
Share of state capacity
0.02%
Rank among solar plants in California
#202 of 937
EIA plant code
59600

Generating units

Individual generating units at Nicolis Solar PV Plant
UnitTechnologyNameplateSummerOnlineStatus
GEN1Solar Photovoltaic20 MW19 MW2016Operating

Nameplate is the maximum rated output; summer capacity is what the unit can reliably deliver on a hot day, which is typically lower.

Similarly sized plants in California

Mordor ES2Battery storage20 MW
NextEra Westside PVSolar20 MW
North Lancaster RanchSolar20 MW
Oro LomaSolar20 MW

About this data

From EIA’s inventory of operable generators, May 2026 release. Capacity is nameplate — the maximum rated output of the equipment, not what the plant actually generates over a year, which depends on how often it runs. A 20 MW solar plant and a 20 MW nuclear plant have the same entry here and produce very different amounts of electricity.

“In service since” is the earliest in-service date among the units still listed, so a site rebuilt around newer equipment can read as younger than the site itself. All California power plants · What California actually generates