CA Manteca 730 Spreckels Ave
Solar power plant · San Joaquin County, California
Details
- Primary fuel
- Solar
- Technology
- Solar Photovoltaic
- Operator
- Catalyze Manteca 730 Spreckels Avenue Microgrid LLC
- County
- San Joaquin County
- Generating units
- 2
- Share of state capacity
- 0.00%
- Rank among solar plants in California
- #438 of 937
- EIA plant code
- 66509
Generating units
| Unit | Technology | Nameplate | Summer | Online | Status |
|---|---|---|---|---|---|
| 18259 | Solar Photovoltaic | 1.5 MW | 1.5 MW | 2024 | Operating |
| B8259 | Batteries | 1.5 MW | 1.5 MW | 2024 | Operating |
Nameplate is the maximum rated output; summer capacity is what the unit can reliably deliver on a hot day, which is typically lower.
Similarly sized plants in California
| Burney Creek | Hydro | 3.0 MW |
| CA - Fresno, City of - SE Surface WTP | Solar | 3.0 MW |
| CalCity Solar 1 | Solar | 3.0 MW |
| Central Antelope Dry Ranch B LLC | Solar | 3.0 MW |
About this data
From EIA’s inventory of operable generators, May 2026 release. Capacity is nameplate — the maximum rated output of the equipment, not what the plant actually generates over a year, which depends on how often it runs. A 3.0 MW solar plant and a 3.0 MW nuclear plant have the same entry here and produce very different amounts of electricity.
“In service since” is the earliest in-service date among the units still listed, so a site rebuilt around newer equipment can read as younger than the site itself. All California power plants · What California actually generates