Coolidge Generation Station
Natural gas power plant · Pinal County, Arizona
Nameplate capacity
1,023 MW
Rank in Arizona
#9
of 200 plants
In service since
2011
May 2011
Details
- Primary fuel
- Natural gas
- Technology
- Natural Gas Fired Combustion Turbine
- Operator
- Salt River Project
- County
- Pinal County
- Generating units
- 18
- Share of state capacity
- 2.38%
- Rank among natural gas plants in Arizona
- #5 of 33
- EIA plant code
- 56948
Generating units
| Unit | Technology | Nameplate | Summer | Online | Status |
|---|---|---|---|---|---|
| 1 | Natural Gas Fired Combustion Turbine | 61 MW | 43 MW | 2011 | Operating |
| 10 | Natural Gas Fired Combustion Turbine | 61 MW | 43 MW | 2011 | Operating |
| 11 | Natural Gas Fired Combustion Turbine | 61 MW | 43 MW | 2011 | Operating |
| 12 | Natural Gas Fired Combustion Turbine | 61 MW | 43 MW | 2011 | Operating |
| 2 | Natural Gas Fired Combustion Turbine | 61 MW | 43 MW | 2011 | Operating |
| 3 | Natural Gas Fired Combustion Turbine | 61 MW | 43 MW | 2011 | Operating |
| 4 | Natural Gas Fired Combustion Turbine | 61 MW | 43 MW | 2011 | Operating |
| 5 | Natural Gas Fired Combustion Turbine | 61 MW | 43 MW | 2011 | Operating |
| 6 | Natural Gas Fired Combustion Turbine | 61 MW | 43 MW | 2011 | Operating |
| 7 | Natural Gas Fired Combustion Turbine | 61 MW | 43 MW | 2011 | Operating |
| 8 | Natural Gas Fired Combustion Turbine | 61 MW | 43 MW | 2011 | Operating |
| 9 | Natural Gas Fired Combustion Turbine | 61 MW | 43 MW | 2011 | Operating |
| COE13 | Natural Gas Fired Combustion Turbine | 50 MW | 42 MW | 2026 | Operating |
| COE14 | Natural Gas Fired Combustion Turbine | 50 MW | 42 MW | 2026 | Operating |
| COE15 | Natural Gas Fired Combustion Turbine | 50 MW | 42 MW | 2026 | Operating |
| COE16 | Natural Gas Fired Combustion Turbine | 50 MW | 42 MW | 2026 | Operating |
| COE17 | Natural Gas Fired Combustion Turbine | 50 MW | 42 MW | 2026 | Operating |
| COE18 | Natural Gas Fired Combustion Turbine | 50 MW | 42 MW | 2026 | Operating |
Nameplate is the maximum rated output; summer capacity is what the unit can reliably deliver on a hot day, which is typically lower.
Similarly sized plants in Arizona
| Red Hawk | Natural gas | 1,127 MW |
| Hoover Dam (AZ) | Hydro | 1,039 MW |
| Coronado | Coal | 822 MW |
| Ocotillo | Natural gas | 806 MW |
About this data
From EIA’s inventory of operable generators, June 2026 release. Capacity is nameplate — the maximum rated output of the equipment, not what the plant actually generates over a year, which depends on how often it runs. A 1,023 MW solar plant and a 1,023 MW nuclear plant have the same entry here and produce very different amounts of electricity.
“In service since” is the earliest in-service date among the units still listed, so a site rebuilt around newer equipment can read as younger than the site itself. All Arizona power plants · What Arizona actually generates